2021 Street Resurfacing

Street Resurfacing

The next phase of our 10-year street resurfacing plan gets underway next month. See the images below for what areas we will be resurfacing. Here’s what to know:

  • This is a rolling operation, meaning sections of street will only be closed for short amounts of time, but will be accessible for the duration of the project. If you live in this area, you will be able to drive on the street shortly after milling and shortly after asphalting.
  • Milling will start April 5 and take about a month to complete.
  • Resurfacing with ultra-thin bonded asphalt (UBAS) will begin in early June and take 45-60 days to complete.
  • No Parking signs will be placed on streets throughout the project. We ask that all cars be removed from the street by 7 a.m. the morning after the no parking signs are placed until the milling or resurfacing work on that street is concluded.

Click here to find more information about the City of Papillion's 10-year Pavement Management Plan.

Street Resurfacing


Facebook Twitter Email

Other News in City News

HR

We are hiring! Join our team!

Posted on: June 7, 2021
City of Papillion logo

2020 Water Quality Report

Posted on: March 30, 2021